Question: In the work flow chart below, the average end times of each activity are given in days. a- Find the critical path. . Find the

In the work flow chart below, the average end

In the work flow chart below, the average end times of each activity are given in days. a- Find the critical path. . Find the total duration of the project. b- Does the total duration of the project change if the completion time of the "4-6" activity reaches 10 days? c- The average duration of the "3-2" activity should conform to the normal distribution with 6 and standard deviation of 3. According to this Find the probability that the project completion time is more than 54 days. 7 10 T 8 12 12 6 13 11 13