Question: In your project A work package wase exprcted to cost SAR 3000 to complete it was originally scheduled ro be finished today. So far you
In your project A work package wase exprcted to cost SAR 3000 to complete it was originally scheduled ro be finished today. So far you have actually spend SAR2500 your team estimate that they have complete three fourth of the work calculate the following Cost Variance? Schedule Variance? Cost performance index? Schedule performance index? Cost-scheduled index Estimate cost to complete? Estimate cost at complete?