Question: In your text, Chapter 9 , Project Scheduling: PERT / CPM on page 4 4 5 , complete problem 6 which shows a project network
In your text, Chapter Project Scheduling: PERTCPM on page complete problem which shows a project network with activity times. Answer the following:
Identify the critical path.
How much time will be needed to complete this project?
Can activity D be delayed without delaying the entire project? If so by how many weeks?
Can activity C be delayed without delaying the entire project? If so by how many weeks?
What is the schedule for activity
In your text, Chapter Project Scheduling: PERTCPM on page complete problem which states: Embassy Club Condominium, located on the west coast of Florida, is undertaking a summer renovation of its main building. The project is scheduled to begin May and a September week completion date is desired. The condominium manager identified the following renovation activities and their estimated times in the table below.
Using the data in the above statement and in the table below, answer the following questions:
Draw a project network.
What are the critical activities?
What activity has the most slack time?
Will the project be completed by September
Condominium Renovation Activities and Estimated Times
tableActivityImmediate Predecessor,TimeABCA B CDC DEAFD FGEH
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock