Question: Include this In y 31 Determine iff the project can be completed in 45 weeks. (NOTE: This should show on your project, but please also

Include this In y 31 Determine iff the project can be completed in 45 weeks. (NOTE: This should show on your project, but please also call it out in your submission notes with a Yes or No and the number off weeks that will be needed). 4) Provide an assessment off the Network Sensitivity in your submission comments. Hint: Review the Schedule Table} Activity Activity ID Description Activity Predecessor Time (weeks] 1 Staff None 2 Develop market program 3 3 Select channels off distribution 1 4 Patent 1 12 5 Pilot production 1 4 Test market 5 4 Ad promotion 2 4 set up for production 4.6 16