Question: The optical disk project team has started gathering the information necessary to develop the project networkpredecessor activities and activity times in weeks. The results of
The optical disk project team has started gathering the information necessary to develop the project networkpredecessor activities and activity times in weeks. The results of their meeting are found in the following table. The project team has requested that you create a network for the project, and deter-mine if the project can be completed in 45 weeks.
Please show all work including formulas. Thanks