The general overhead for the company is anticipated to be $375,420 this year The company anticipates doing
Fantastic news! We've Found the answer you've been seeking!
Question:
The company anticipates doing 5 major jobs this year
The current job is anticipated to take 4 months to complete
The home office costs $2500 a month to rent
The temporary office for the current job is costing the company $350/month
The project manager for the current job will cost $6500/month and will be needed for the entire duration of the project
The civil superintendent will cost $5500 a month, but will only be required for 2 weeks
The concrete superintendent will be needed for 1 month and will cost $4000/month
The cleanup superintendent will be needed for the entire project and will cost $2000/month
Sanitary facilities will be needed for the duration of the project and will cost $7500/month
The generators used to provide power to the job site will cost $5500/month but will only be needed for the first 3 months of the project
The profit for this project is to be 20% of the indirect overhead
Labor and materials cost for the project are $750,
Calculate and display the estimated direct and indirect overhead.
Calculate the estimated profit and display any sub items that go into any of the above categories