Question: Indented activities and summary tasks are used to a . reflect the hierarchy in the work breakdown structure. b . finalize the project plan. c
Indented activities and summary tasks are used to
a reflect the hierarchy in the work breakdown structure.
b finalize the project plan.
c simplify the project.
d show the level of complexity of the project.