Question: ndented activities and summary tasks are used to a . simplify the project. b . show the level of complexity of the project. c .
ndented activities and summary tasks are used to
a simplify the project.
b show the level of complexity of the project.
c reflect the hierarchy in the work breakdown structure.
d finalize the project plan.