Indirect Costs on a project are Rs. 50/day. A can be crashed by 3 days at a cost of Rs. 40/day.
B can be crashed by 4 days at a cost of Rs. 60/day. What is the optimal strategy?
1.Crash A by 3 days and B by 4 days
2.Crash only A by 3 days
3. Crash only B by 4 days
4 Do not crash either activity.
THE QUESTION PERTAINS TO PROJECT MANAGEMENT