Question: Individual activity Instruction Based on our previous lesson: Please answer these simple Project calculations. End of Week 10 $83,000 was budgeted $86,000 was actually expended

Individual activity Instruction Based on our previous lesson: Please answer these simple Project calculations. End of Week 10 $83,000 was budgeted $86,000 was actually expended $73,000 was the earned value of work actually performed 1. Calculate the Project Cost Performance Index? 2. Calculate the Project Cost Variance? *** You are given the time until 10PM today to submit this task in the dedicated page (UROX Module 5-F2F Class/Hybrid Discussion (No Grading)