Question: Individual Assignment - Critical Path Method Schedule the following activities are part of a project to be scheduled using CPM . table [ [

Individual Assignment - Critical Path Method
Schedule the following activities are part of a project to be scheduled using CPM.
\table[[Activity,\table[[Immediate],[predecessor]],\table[[Time],[(Weeks)]]],[A,-,1],[B,A,4],[C,A,3],[D,B,2],[E,C, D,5],[F,D,2],[G,F,2],[H,E, G,3]]
Draw the network (4 Points)
What is the critical path? (2 points)
How many weeks will it take to complete the project? (2 points)
Which activities have slack, and how much? (2 points)