Question: Individual Project: Schedule, Defining Predecessors, Duration, and Critical Path The project is sustainable urban farming As you continue to work with schedules, remember there are
Individual Project: Schedule, Defining Predecessors, Duration, and Critical Path
The project is sustainable urban farming
As you continue to work with schedules, remember there are five major elements affecting project completion: logical order (or sequence) of project tasks, duration of each task, the number of resources available when needed to complete those tasks, imposed dates, and cash flow. When building schedules in MS Project, you will find it helpful to keep these limitations in order.
For this assignment, follow the below steps to complete the Microsoft Project Exercise for your individual chosen project:
- Review the below Microsoft Project tutorial video:
- Setting Up the Schedule Using MS Project (Click Here)
- Defining Precedence, Duration, and Critical Path Using MS Project (Click Here)
- Update the schedule of your Microsoft Project file for your individual project using the below criteria:
- Use the first day of the sixth week of this semester for the project's start date.
- Configure working days to be Monday thru Friday 9am - 6pm.
- Configure the last full week of this semester as non working days.
- Include the last five Saturdays of this semester as working days.
- Configure the Time Scale to display three tiers (Months, Weeks, Days)
- Update the following items in your individual project file:
- Define Predecessors (Task Dependences)
- Assign Duration Estimates
- Identify Critical Path
- Upload your Microsoft Project file to the "Individual Project: Schedule, Defining Predecessors, Duration, and Critical Path" link above
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
