Question: Individual Risk plan and Individul EVM plan Project Budget Notes Hourly wage rates Project Manager (PM) hourly wage rate is $45/hr Company employee hourly wage
Individual Risk plan and Individul EVM plan
Project Budget Notes
Hourly wage rates
Project Manager (PM) hourly wage rate is $45/hr
Company employee hourly wage rate is $22/hr
Material Quotes
Cabinets $8,343
Sink/faucet $1,070
Appliances $3,095
Paint $760
Granite countertop $3,100
Tile materials $1,350
|
| Work package | Duration (days) | Notes |
| 1.1 | Demolition: remove all old appliances, cabinets, and flooring | 3 | PM works 1 hour on day 1 (2) employees each work 8 hours on day 1 (1) employee works 8 hours on day 2 |
| 1.2 | Haul away materials/debris | 1 | (2) employees each work 4 hours |
| 2.1 | Order cabinets | 2 | PM works 2 hours on day 1 (measuring) PM works 2 hours on day 2 (ordering/paying for material) |
| 2.2 | Order sink/faucet | 1 | PM works 1 hour (ordering/paying for material) |
| 2.3 | Order appliances | 1 | PM works 1 hour (ordering/paying for material) |
| 2.4 | Order paint | 2 | PM works 1 hour (ordering/paying for material) |
| 3.1 | Create countertop subcontract | 1 | PM works 2 hours (ordering material) Subcontractor requires 50% deposit on countertop material cost |
| 3.2 | Create tile subcontract | 3 | PM works 2 hours on day 1 (planning layout) PM works 2 hours on day 2 (meeting subcontractor) |
| 3.3 | Create painting subcontract | 1 | PM works 1 hour (meeting subcontractor) |
| 4.1 | Install cabinets | 3 | PM works 1 hour on day 1 (2) employees each work 6 hours on days 1 and 2 (1) employee works 6 hours on day 3 PM works 1 hour on day 3 |
| 4.2 | Install countertop | 1 | Subcontractor charges $350 for labor Subcontractor collects remaining 50% countertop material cost |
| 4.3 | Install tile floors | 4 | Subcontractor charges $1100 for labor Subcontractor collects tile material cost |
| 4.4 | Install sink/faucet | 1 | (1) employee works 8 hours |
| 4.5 | Install appliances | 2 | (2) employees each work 8 hours on days 1 and 2 |
| 5.1 | Paint walls & ceiling | 4 | Subcontractor charges $1600 for labor |
| 6.1 | PM Inspection/punchlist | 3 | PM works 2 hours (1) employee works 4 hours |
| 6.2 | Walk through / acceptance | 1 | PM works 1 hour |