Question: Information for the Time-Cost Model Exercise Crash Normal Immediate Normal Time Cost Crash Task Time Predecessors (weeks) Cost (weeks) A NONE $5,000 $13,000 W N

Information for the Time-Cost Model Exercise Crash Normal Immediate Normal Time Cost Crash Task Time Predecessors (weeks) Cost (weeks) A NONE $5,000 $13,000 W N B A $10,000 $20,000 A A A $6.000 $6,000 UT A $4,000 $8,000 B & C A $4,000 $9,000 D & E N $5,000 $9,000 F N $3,000 $6,000 Your firm is creating new marketing material for an existing product in order to increase customer demand. The table below lists the steps that need to be complete. You recently found out if he project isn't complete by the end of the year this product will have to be discontinued. What is the duration of the project after all crashing is complete? 13 12 10 0 11
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
