Question: Initial schedule Fully crashed schedule activity cost ( 0 0 0 ' s ) Duration ( days ) cost ( 0 0 0 ' s

Initial schedule
Fully crashed schedule
activity cost (000's) Duration (days) cost (000's) Duration (days)
\table[[A,5,4,9,3],[B*,10,5,13,4]]
\table[[C,3.5,2,7,1]]
\table[[D*,4.5,6,8.5,4]]
\table[[E,1.5,3,4,2]]
\table[[F,7.5,8,12.5,7],[G*,3,7,5.5,6],[H,2.5,6,5.5,5]]
a) Identify the sequence of the activities to be crashed in the first 3 crashing steps.
b) What is the duration and cost of the project after the first three crashing steps?
c) If a penalty charge of $5000 per day is imposed past day 18, which activities do you crash and by how far?
 Initial schedule Fully crashed schedule activity cost (000's) Duration (days) cost

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!