Question: INS377 IT Project Management Use MS Project to create a Work Breakdown Structure (WBS) leading to completion of a new project Task Duration Predecessor A

INS377 IT Project Management

Use MS Project to create a Work Breakdown Structure (WBS) leading to completion of a new project

Task

Duration

Predecessor

A

4

B

3

A

C

2

B

D

3

C

E

3

D

F

2

C

G

2

B

H

7

G

I

2

E, F,H

QUESTIONS:

  1. Task C is delayed by one day. What impact would this have on the completion date of the project? Why?
  2. Task B is delayed by one day. What impact would this have on the completion date of the project? Why?
  3. The project manager reduces the durations of tasks D and F by one day each. How will this affect the finishing date of the project?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!