Question: INS377 IT Project Management Use MS Project to create a Work Breakdown Structure (WBS) leading to completion of a new project Task Duration Predecessor A
INS377 IT Project Management
Use MS Project to create a Work Breakdown Structure (WBS) leading to completion of a new project
| Task | Duration | Predecessor |
| A | 4 |
|
| B | 3 | A |
| C | 2 | B |
| D | 3 | C |
| E | 3 | D |
| F | 2 | C |
| G | 2 | B |
| H | 7 | G |
| I | 2 | E, F,H |
QUESTIONS:
- Task C is delayed by one day. What impact would this have on the completion date of the project? Why?
- Task B is delayed by one day. What impact would this have on the completion date of the project? Why?
- The project manager reduces the durations of tasks D and F by one day each. How will this affect the finishing date of the project?