Question: Installing a muffler at Barut Garage, Inc. involves a five work tasks. Azra has timed workers performing these tasks seven times, with the results (in

Installing a muffler at Barut Garage, Inc. involves a five work tasks. Azra has timed workers performing these tasks seven times, with the results (in minutes) shown in the following table.

No

Tasks

1

2

3

4

5

6

7

PR

1

Select correct mufflers

3

5

4

4

5

5

6

110

2

Remove old muffler

7

7

7

5

8

6

5

120

3

Install new muffler

14

13

11

14

15

12

13

90

4

Inspect the work

4

4

3

4

3

3

4

110

5

Complete paperwork

7

10

7

10

8

10

9

120

Given that Azra does not want an error of more than 0.03 and a confidence level less than 0.90 answer the following: Provide the z-score: Round to the nearest hundredth, for example 4.22 Does the number of observations for the following tasks warrant such confidence level? Enter YES or NO. Task # 3 Install new muffler : Task # 5 Complete paperwork : What are the required numbers of observations for these tasks? Enter the number. Task # 3 Install new muffler : Task # 5 Complete paperwork : Assume that the number of observations for the following tasks justifies the confidence level and accuracy mentioned above. Also note that Azra factors in a total of fatigue and personal allowance of 0.10 applied to job time. Provide the following results from your solution:

Task

Normal Time*

Standard Time*

# 2 Remove old muffler

min

min

# 4 Inspect the work

min

min

Provide the total standard time* for the whole job: _____ minutes. *Round to the nearest hundredth, for example 8.45 minutes

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!