Question: Instructions: Answer all questions for each problem. Upload your answers and your codes as pdf file on blackboard. Questions: Question 01: Consider that the following

Instructions: Answer all questions for each problem. Upload your answers and your codes as pdf file on blackboard. Questions: Question 01: Consider that the following Jobs has to be allocated to a single machine jobs 1 2 3 4 5 6 7 8 9 10 p_(j) 12 16 8 9 13 12 16 10 21 22 d_(j) 33 15 43 47 34 48 78 15 63 49 a) Assume the following sequence: 1 > 2 > 3 > 4 > 5 > 6 > 7 > 8 > 9 > 10. Calculate the following paramters Makespan Flow time Total tardiness Number of tardy jobs b) Use the spt rule and evaluate Makespan Flow time Total tardiness Number of tardy jobs