Question: Instructions: Answer parts a, b and c. A company needs to achieve a production of 250 units per 8-hour day using a production line. The

Instructions: Answer parts a, b and c.

A company needs to achieve a production of 250 units per 8-hour day using a production line.

The list of tasks with their precedence relationships and times is as follows:

Task

Predecessor

Time (Secs)

A

-

50

B

A

75

C

-

30

D

C

45

E

B, D

40

F

-

40

G

F

80

H

D, G

60

I

E, H

40

J

I

120

a) Draw the network

b) Provide the best possible balance

c) Determine the balancing efficiency