Question: The following information is given for the set of activities: Activity Predecessor(s) Duration(day) A B C D E A, B B, C 4 3
The following information is given for the set of activities: Activity Predecessor(s) Duration(day) A B C D E A, B B, C 4 3 6 5 B1) Draw Activity on Arrow Diagram (AoA) and mention EET's (earliest event time) and LET's (latest event times) B2) Draw Activity on Node Diagram (AoN) and calculate Total Project Time (TPT) and Critical Path by calculating necessary event /activity durations.
Step by Step Solution
3.42 Rating (149 Votes )
There are 3 Steps involved in it
Question B1 Solution According to Question Firstly we can draw the Network diagram and above given Diagram is shown Activity On Arrow AOA Network Diag... View full answer