Question: Instructions Carefully read the case study and answer the related questions. Use complete sentences and paragraphs to answer the questions and explain your answers. Save

Instructions
Carefully read the case study and answer the related questions.
Use complete sentences and paragraphs to answer the questions and explain your answers.
Save this completed assignment as YourLastName_FirstInitial_CS2
Submit your completed document to the eCentennial dropbox for this assignment on or before the due date of the week 14.
Task time estimates for a production line setup project at Robert Klassens Ontario factory are as follows:
You have been hired as the manager of this project; the company has asked you to complete the following:
1. Develop a CPM/PERT AON network. (8 Marks)
2. Determine the critical path of the project. (8 Marks)
3. What is the total project completion time? (8 Marks)
4. Draw a GANTT chart for the project?. (7 Marks)
5. Your senior manager is questioning What is the use of Gantt charts in project management? Please provide an explanation as to why a Gantt would be used and the benefits. (4 Marks)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!