Question: Instructions Complete the critical path question and submit by October 23 EOD. 1 mark for participating and completing all questions. OR 2 marks for a

Instructions Complete the critical path question and submit by October 23 EOD. 1 mark for participating and completing all questions. OR 2 marks for a completely correct answer Weekly Assignment Individual (2\%) Due Week 8 The following is an actual previous midterm exam question that focused on networks, critical paths and slack times. Complete individually and hand-in before the end of class Question \#4 (Total 14 marks) Show all your work a) Given the following activities, predecessors, and times, draw a critical path network diagram (5 marks) b) What is the critical path? ( 3 marks) c) How long will it take to complete the project? (2 marks) d) What is the slack time for activity C? (2 marks) e) What is the slack time for activity I? (2 marks)