Question: Weekly Assignment ( 2 % ) Due Week 6 The following is an actual previous midterm exam question that focused on networks, critical paths and
Weekly Assignment Due Week
The following is an actual previous midterm exam question that focused on networks, critical paths and slack times. Complete the assignment individually and handin before Feb :
Show all your work
a Given the following data, draw a critical path network diagram.
b What is the critical path?
c How long will it take to complete the project?
d What is the slack time for activity C
e What is the slack time for activity I?
Activity
Time days
A
B
C
D
E
B
A
F
A
G
D
E
Grading scheme:
: no submission
: participating and completing all questions
: completely correct answer
H
C
Due Feb : late penalty until Feb : late penalty afterwards
I
Immediate Predecessor
F G
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock