Question: Instructions: Read and complete the attached assignment. Submit the completed assignment using Word (.doc) or Excel (.xls) documents. Answer all questions and show calculations. Check
Instructions:
- Read and complete the attached assignment.
- Submit the completed assignment using Word (.doc) or Excel (.xls) documents.
- Answer all questions and show calculations.
- Check the Rubric
Assignment:
Four projects A, B, C and D are under consideration and they each have risks associated with the producing benefits. Based on the information given in the table below, which project is more desirable for the company?
Project A | Project B | Project C | Project D | ||||
EUAW | Prob. | EUAW | Prob. | EUAW | Prob. | EUAW | Prob. |
$2,000 | 0.2 | $3,000 | 0.1 | -$5,000 | 0.2 | $4,000 | 0.4 |
$1,500 | 0.5 | -$2,500 | 0.4 | $6,500 | 0.5 | $2,500 | 0.3 |
$3,000 | 0.3 | $3,500 | 0.5 | $1,000 | 0.3 | -$2,000 | 0.3 |
- Calculate the EUAW for each project
- Determine which project should be recommended

Project A Project B Project C Projec EUAW Prob. EUAW Prob. EUAW Prob. EUAW $2,000 0.2 $3,000 0.1 0.2 $4,000 $5,000 $1,500 0.5 0.4 $6,500 0.5 $2,500 $2,500 $3,000 0.3 $3,500 0.5 $1,000 0.3 $2,000 ect A Project B Project C Project D w Prob. EUAW Prob. EUAW Prob. EUAW Prob. 00 0.2 $3,000 0.1 0.2 $5,000 $4,000 0.4 DO 0.5 0.4 $2,500 $6,500 0.5 $2,500 0.3 00 0.3 $3,500 0.5 $1,000 0.3 0.3 $2,000
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts