Question: Instructions: Use a single excel file to complete the following problem, and then submit it to Blackboard using the designated link. The following table lists
Instructions: Use a single excel file to complete the following problem, and then submit it to Blackboard
using the designated link.
The following table lists details of completing each task for a construction project:
Draw the network for this project.
Do a forward pass and a backward pass.
Calculate the slack.
What is the critical path?
What is the total normal project completion time?
What is the total cost for normal project completion?
How much will it cost to crash the project completion by one day What is the new total normal
cost for project completion
Can the project completion be crashed by two days? Why or why not? If so how?
What will be the new total normal cost for project completion if it is crashed by two days?
What is the minimum time for project completion?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock