Question: Introduction to project management 2- (PERT) . In (PERT) when finding the duration for each path, we choose the longest path as the least time

Introduction to project management
2- (PERT) . In (PERT) when finding the duration for each path, we choose the longest path as the least time required to implement the project. Prove that we cannot complete the project in less than the longest path duration and not the shortest path? (2 marks)Step by Step Solution