Question: Introduction to project management 1- (PERT) . In (PERT) when finding the duration for each Path, if there are two paths, they are the longest.

Introduction to project management
1- (PERT) . In (PERT) when finding the duration for each Path, if there are two paths, they are the longest. . Which is the critical path, and what are the critical activities in this case? (1 marks) 2- (PERT) . In (PERT) when finding the duration for each path, we choose the longest path as the least time required to implement the project. Prove that we cannot complete the project in less than the longest path n and not the shortest path? (2 marks) 1 of 3 WStep by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
