Question: IRR Compute the IRR statistic for Project E and note whether the firm should accept or reject the project with the cash flows shown as
IRR Compute the IRR statistic for Project E and note whether the firm should accept or reject the project with the cash flows shown as follows if the appropriate cost of capital is 8 percent.
Project E
| Time | 0 | 1 | 2 | 3 | 4 | 5 |
| Cash Flow | -$1,000 | $350 | $480 | $520 | $300 | $100 |