Question: IRR Compute the IRR statistic for Project E and note whether the firm should accept or reject the project with the cash flows shown as
IRR Compute the IRR statistic for Project E and note whether the firm should accept or reject the project with the cash flows shown as follows if the appropriate cost of capital is 8 percent. Show Calculations
Project E
Time 0 1 2 3 4 5
Cash Flow -1000 350 480 520 300 100