Question: is a document that shows work that still needs to be done on a construction project after substantial completion punchlist Work Order Change Order Supplemental

is a document that shows work that still needs to be done on a construction project
after substantial completion
punchlist
Work Order
Change Order
Supplemental Instruction
is a document that shows work that still needs to