Question: ______ is a task on which a subsequent (following) task depends in a project schedule. A. Precedence relations B. Predecessor C. Precedence constrains D. Successor

______ is a task on which a subsequent (following) task depends in a project schedule. A. Precedence relations B. Predecessor C. Precedence constrains D. Successor