Question: _________ is the difference between the earned value and the baseline line to date. (3 points) Select one: a. Schedule variance b. Cost variance c.
_________ is the difference between the earned value and the baseline line to date. (3 points) Select one: a. Schedule variance b. Cost variance c. Actual cost d. Earned value