Question: Is the project over or under budget? Note: Enter 1 for over budget and O for under budget. Term BAC EV Value 257,400 41,250 38,900



Is the project over or under budget? Note: Enter 1 for over budget and O for under budget. Term BAC EV Value 257,400 41,250 38,900 48,200 PV AC Is the project ahead of or behind schedule? Note: Enter 1 for ahead and O for behind schedule. Term BAC EV PV Value 199,900 72,300 38,300 57,100 AC Your Answer: Answer Calculate CPI for the below figures and enter the value rounded to two decimal places. Note: Do not enter as percentage. For example, a value of 25% must be entered as 0.25 Term BAC EV PV Value 208,300 124,000 28,400 24,500 AC Your