Question: Is there a cost overage? If so, how much is it? Explain Is the schedule ahead or -behind? Explain. (SPI values) Overall, does the project

Is there a cost overage? If so, how much is it?

  1. Is there a cost overage? If so, how much is it? Explain
  1. Is the schedule ahead or -behind? Explain. (SPI values)
  1. Overall, does the project appear to be in control? Explain. (Management perspective)
2. At week 24 of a project to shoot a television commercial, the project manager is worried about her budget since costs have risen to $7,500. Duration (weeks) Bud- get, $ % Completed 6 900 100 6 1200 100 a 6 1200 100 Prede- Activity cessors a: Write script b: Screen actors c: Select actors d: Contract studio e: Obtain props b, c f: Schedule date b, c, d g: Shoot de commercial a 12 1800 100 14 100 1400 1500 10 40 16 800 0 Planned value for week 24 18 d. 12 28 1710 2,6 42 End Start 12 0,6 42 9.16 6 b.6 26: 0.14 a. Calculate the following (Formulas are provided in the Appendix) PV = EV = AC = CPI = SPI = CSI =

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!