Question: is this answer correct: 2 a . Paths: 1 - 2 - 5 - 7 = 4 + 7 + 5 = 1 6 weeks
is this answer correct: a
Paths:
weeks
weeks
weeks
weeks
weeks
weeks
Critical path longest path ADH
Length weeks
b
Activity A is critical, therefore, slack
c
We shall crash H by weeks, then A by week
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock