Question: is this answer correct: 2 a . Paths: 1 - 2 - 5 - 7 = 4 + 7 + 5 = 1 6 weeks

is this answer correct: 2a.
Paths:
1-2-5-7=4+7+5=16 weeks
1-3-5-7=6+3+5=14 weeks
1-3-6-7=6+5+2=13 weeks
1-4-3-5-7=5+3+5=13 weeks
1-4-3-6-7=5+5+2=12 weeks
1-4-6-7=5+4+2=11 weeks
Critical path =longest path =1-2-5-7(A-D-H)
Length =16 weeks
2b.
Activity A is critical, therefore, slack =0
2c.
We shall crash 5-7(H) by 2 weeks, then 1-2(A) by 1 week