Question: Is this correct? On day 51 a project has an earned value of $580, an actual cost of $570, and a planned cost of $580.
Is this correct?

On day 51 a project has an earned value of $580, an actual cost of $570, and a planned cost of $580. Compute the SV, CV, and CPI for the project. (Round your "CPI" answer to 2 decimal places.) The CV is The SV is The CPI is $ $ 10 0 0.01