When looking at the life of a project plan, it is useful to graph and outline the
Fantastic news! We've Found the answer you've been seeking!
Question:
When looking at the life of a project plan, it is useful to graph and outline the cost variance (CV), and schedule variance (SV). Determining progress, or lack of progress, provides essential information to assess a given project. Complete exercise 2 in chapter 13 of the textbook. Given the data provided, in an excel spreadsheet, PowerPoint, or other appropriate method of delivery,
Determine the following: Schedule Variance (SV) Cost Variance (CV) Schedule Performance Index (SPI) Cost Performance Index (CPI) In 250-300 words, answer the questions provided with the exercise.. Should the project continue to improve? On day 51 a project has an earned value of $600, an actual cost of $650, and a planned cost of $560. Compute the SV, CV, and CPI for the project. What is your assessment of the project on day 51?
Related Book For
Managing Operations Across the Supply Chain
ISBN: 978-0078024030
2nd edition
Authors: Morgan Swink, Steven Melnyk, Bixby Cooper, Janet Hartley
Posted Date: