Question: is used to systematically identify all project risks (i) by grouping potential causes of risk or (ii) by grouping risks according to the project objective
is used to systematically identify all project risks (i) by grouping potential causes of risk or (ii) by grouping risks according to the project objective on which each risk may affect.
a)Risk breakdown structure
b)Risk register
c)Work breakdown structure
d) Risk identification