Question: It is said that a delay in critical path activity will delay the project, while a delay in a noncritical path activity will not necessarily
It is said that a delay in critical path activity will delay the project, while a delay in a noncritical path activity will not necessarily delay the project. Explain the need to specify "not necessarily."
Step by Step Solution
3.38 Rating (157 Votes )
There are 3 Steps involved in it
The not necessarily specification is crucial because while a delay in a noncritical path acti... View full answer