Question: Q 3 ( 2 0 points ) The project information is given below ( under normal conditions, in weeks ) . A ( 6 points

Q3(20 points) The project information is given below (under normal conditions, in weeks).
A (6 points) Under normal conditions, which path is the critical path, and what is the project
duration? Please use two-pass (forward/backward pass) method (3 points for the two-pass
method, 2 points for the critical path, 1 point for project duration.)
Critical Pat
Project Duration:
(don't forget time units!)
B.(2 points) Suppose lack, the only employee responsible for activity C wants to take a two-week
vacation during weeks 3 and 4. Can you allow Jack to take the vacation and still complete the
project without delay? Briefly justify your answer.
C (2 points) Suppose that activities B, C, E, F, and I can be crashed. The normal time, crash time,
normal cost and crash cost are shown in the table below. What is the weekly crash cost of each
activity? (Crash time is the shortest possible activity time and crash cost is the cost associated
with the crash time)
D.(10 points) Suppose the management instead wants the project to be completed in 14
weeks. How can you achieve thls goal at minimum cost? Please report your crashing steps in
the table below. (The table size does not imply number of steps.)Q3(20 points) The project information is given below (under normal conditions, in weeks).
A.(6 points) Under normal conditions, which path is the critical path, and what is the project
duration? Please use two-pass (forward/backward pass) method (3 points for the two-pass
method, 2 points for the critical path, 1 point for project duration.)
Critical Path(s):
Project Duration:
(don't forget time unitsl)
B.(2 points) Suppose Jack, the only employee responsible for activity C wants to take a two-week
vacation during weeks 3 and 4. Can you allow Jack to take the vacation and still complete the
project without delay? Briefly justify your answer.
C.(2 points) Suppose that activities B, C, E, F, and I can be crashed. The normal time, crash time,
normal cost and crash cost are shown in the table below. What is the weekly crash cost of each
activity? (Crash time is the shortest possible activity time and crash cost is the cost associated
with the crash time)
D.(10 points) Suppose the management instead wants the project to be completed in 14 weeks. How can you achleve this goal at minimum cost? Please report your crashing steps in the table below. (The table size does not imply number of steps.)
\table[[\table[[Project Duration],[(weeks)]],Critical Path(s),\table[[Crashable Tasks on Critical Paths]],\table[[Best Option],[[weeks to],[crash]]]],[,,,],[,,,]]
 Q3(20 points) The project information is given below (under normal conditions,

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!