Question: It is the Operations Research question. It is the subject of MODELING. During the construction of a house, six joists of 24 ft each must

It is the "Operations Research" question. It is the subject of "MODELING".
During the construction of a house, six joists of 24 ft each must be trimmed to the correct length of 23 ft. The operations for cutting a joist involve the following sequence: Operation Time (seconds) 1. Place joist on saw horses 2. Measure correct length (23 ft) 3. Mark cutting line for circular saw 4. Trim joist to correct length 5. Stack trimmed joist in a designated area 15 5 5 20 20 Three persons are involved: Two loaders must work simultaneously on operations 1, 2, and 5, and one cutter handles operations 3 and 4. There are two pairs of saw horses on which untrimmed joists are placed in preparation for cutting, and each pair can hold up to three side-by-side joists. Suggest a good schedule for trimming the six joistsStep by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock