Question: It is week 1 and there are currently 2 0 As in stock. We need 3 0 0 As at the start of week. 5

It is week 1 and there are currently 20 As in stock. We need 300 As at the start of week. 5. there are scheduld recents planned for week 3 and week 4 of 120 As each and A has a lead time of 3 weeks, when and how la rec a an ardes chould be placed to meet the requirement of 300 As?
Week 3,40 As
O Week 3,60 As
O Week2,40As
O Week 2,60As
O Week3,300As
 It is week 1 and there are currently 20 As in