Question: It is widely accepted that the work breakdown structure should be decomposed into smaller and smaller tasks until the average work package: Is at a

It is widely accepted that the work breakdown structure should be decomposed into smaller and smaller tasks until the average work package:
Is at a level of detail that suits the project manager's status reporting need
Can be accomplished by one person in one week
Is no more than 80 hours of duration
Is no more than 80 labour hours of effort