Question: It project management d. 7 weeks Clear my choice An activity being analyzed under PERT was judged to most likely have a duration of 38

It project management
d. 7 weeks Clear my choice An activity being analyzed under PERT was judged to most likely have a duration of 38 days. When considering the time it would take to complete the activity if every relevant factor went well, it was estimated to take 20 days and even under the worst case imaginable, the task would be take 50 days. The estimates PERT duration of that activity is: Select one: O a. 18 days O b. 43 days O c. 37 days O d. 28 days O e. 25 days AGE NEXT PAGE