It takes at least _______days to finish the following project? ACTIVITIES TIMES IMMEDIATE PREDECESSOR(S) A. Obtain franchise
Fantastic news! We've Found the answer you've been seeking!
Question:
It takes at least _______days to finish the following project?
ACTIVITIES | TIMES | IMMEDIATE PREDECESSOR(S) |
A. Obtain franchise | 30 days | None |
B. Rent facility | 10 days | A |
C. Equip facility | 7 days | B |
D. Recruit&Train staff | 15 days | B |
E. Pass safety inspection | 5 days | C, D |