It took 200 hours to make the first unit of a product. After the second and third
Fantastic news! We've Found the answer you've been seeking!
Question:
It took 200 hours to make the first unit of a product. After the second and third units were made, the learning curve was estimated to be 75%. At $120 per hour, what is the total labour bill for all four units? (rounded to the nearest whole number)
Please show the steps involved in arriving at the answer to this question.
Posted Date: