Question: It was determined that three time estimates would be used in planning a project. The estimates for task E in weeks 5, 6, and 10,

It was determined that three time estimates would be used in planning a project. The estimates for task E in weeks 5, 6, and 10, respectively, were for optimistic, most likely, and pessimistic times. What is the expected time for this task?