Question: It was determined that three time estimates would be used in planning a project. The estimates for task G (in weeks) 4, 6, and 12,

It was determined that three time estimates would

It was determined that three time estimates would be used in planning a project. The estimates for task G (in weeks) 4, 6, and 12, respectively, were for optimistic, most likely, and pessimistic times. What is the standard deviation for this task? O A. 1.78 OB. 0.94 OC. 0.44 OD. 1.33