Question: Item 2 4 3 . 2 2 points eBook Hint Print References Check my work Check My Work button is now enabled Item 2 4

Item24
3.22
points
eBook Hint Print References Check my work Check My Work button is now enabled Item 24
EX6-10(Algo) K. Nelson, project manager of Print...
K. Nelson, project manager of Print Software, Inc., wants you to prepare a project network; compute the early, late, and slack activity times; determine the planned project duration; and identify the critical activities. His assistant has collected the following information for the color printer drivers software project:
ID Description Predecessor Time
(days)
A External specifications None 2
B Review design features A 5
C Document new features A 5
D Write software A 70
E Program and test B 60
F Edit and publish notes C 1
G Review manual D 3
H Alpha site E, F 10
I Print manual G 20
J Beta site H, I 30
K Manufacture J 30
L Release and ship K 5

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock