Question: Item: A Quantity on Hand: 35 Forecast Customer orders (booked) Projected on-hand inventory MPS quantity 1 18 15 2 20 17 3 28 9 Order

Item: A Quantity on Hand: 35 Forecast Customer orders (booked) Projected on-hand inventory MPS quantity 1 18 15 2 20 17 3 28 9 Order Policy: 60 units Lead Time: 1 week Week 4 26 17 5 21 11 6 27 0 7 33 7 8 41
 Item: A Quantity on Hand: 35 Forecast Customer orders (booked) Projected

\begin{tabular}{lr} \hline Item:A & Order Policy: 60 units \\ QuantitynnHand35LeadTime:1week \\ \hline \end{tabular}